Cape Lambert EPC

Information

Client: Rio Tinto
Location: Cape Lambert, WA
Scope: 1.9km 10” pipeline and delivery station
Date: 2016
Project Length: 8 months
Value: >$20M

Industry

Oil & Gas

OSDs Role

  • Engineering
  • Procurement
  • Technical Site Support
  • Commissioning

Summary

OSD delivered the EPC of the 1.9km 10” pipeline and delivery station at Cape Lambert, in JV with Monodelphous and KT-Pipelines. The pipeline connected to the existing purged, cut and capped Rio Pipeline (PL8). Mono’s-KT pipelines were responsible for the stations construction for this project.

OSD was responsible for engineering, procurement, regulatory, technical site support/inspection for the station and commissioning. OSD was also appointed operator for PL8 (and the new pipeline) during the commissioning of the interconnected pipeline system.