Client: Invall
Location: Catalonia, Spain
Scope: 135km DN650 Potash Concentrate Pipeline, 135km DN700/DN800 Return Water Pipeline, 6 pumping stations
Date: 2015
Project Length:
Value: $420k

Industry

Potash

OSD’s Role

  • Route selection
  • Rheology laboratory testing
  • Basic engineering
  • Capital and operating cost estimates

Summary

To evaluate the feasibility of a system to transfer both sylvanite and process salts from its proposed mine sites in Spain to a filter plant and port facilities at either Tarragona or Barcelona ICL Iberia. Invall engaged OSD to undertake an Operations Study to evaluate four alternative pipeline routes. Brine from the dewatering facility at the port is to be recycled back to the mine site via a return water pipeline. Preliminary sizing and order of magnitude cost estimates were developed for each option with design throughout at 12.5 and 14 MTPA.

 

 