Randor 1A & 1B Well Test Piping Stress Analysis

Information

Client: Greymouth Petroleum (GPL)
Location: Waitangirua – Wellington, NZ
Scope: Temporary Piping Stress Analysis
Date: 2018
Project Length:
Value:

Industry

Oil & Gas

OSD’s Role

  • Mechanical Engineering Support & Pipe Stressing
  • HAZOP Participation
  • Project Punch-listing & Inspection Participation

Summary

Wellfluids from the wellhead 1A & 1B flow to the Well test separator (temporary piping connection) and then to the Randor Plant. The HAZOP review included a stress analysis of the temporary piping.