Wodgina 2 Gas Pipeline

Information

Client: Mineral Resources (Equipment) Pty Ltd
Location: Pilbara Region, Western Australia
Scope: 80km DN250 Gas Pipeline
Date: 2018 - Current
Project Length:
Value: $2.6M

Industry

Mining

OSD’s Role

  • FEED
  • Detail Design
  • Procurement & Construction Support
  • Commissioning

Summary

MRL is expanding its Wodgina Lithium Project by increasing spodumene production and developing a lithium carbonate refinery.  To support this expansion, a new 50MW gas-fired power station is required with an upgraded gas supply. The existing DN100 gas pipeline is being replaced with a new DN250 gas pipeline.

OSD was engaged by MRL Energy to undertake the FEED for the new pipeline and the subsequent detail design and commissioning for the pipeline system.